Click here for information about the building committee and the subcommittees.

Here we go!

WEB construction has informed us that work on the parking lot and our building project is about to begin! The short-term timeline recently provided by WEB is as follows: Permit – Anticipate receiving that sometime this week. Mobilize to site on Wednesday, 9/19. Start removals on Thursday, 9/20. Reclaim/grinding asphalt...

Continue reading

Tree, bush, and plant removal – FREE!

FROM THE BUILDING COMMITTEE… All of the trees, bushes, and plants located along the following areas of our facility need to be removed for our building project: The immediate area around our current main entrance on McConnell St., including the outside wall that runs along the cry room, band, room,...

Continue reading

Special Voters’ Meeting Called for Sunday, July 29

On July 18 the Building Committee met with representatives from ISG Architects and WEB Construction and were informed of additional requirements by the city of Mankato, as well as some cost increases to various line items, which have resulted in our building project now being over-budget. A special voters’ meeting...

Continue reading

Building Committee Update: Summary of 2018 Activity

January The loan was secured for financing the building project Schematic Design phase of the project was completed The building committee met with ISG to review a tentative/preliminary project schedule The Design Development phase began, which involved the research and selection of building systems/materials and floor/wall coverings that would be...

Continue reading

Building Committee Update – May 20

The Building Committee met on Tuesday, May 15. The interior designer from ISG brought samples of many of the finishes and colors that had been selected by the user groups for various areas of new construction. The committee discussed and provided input on the various choices and approved the items...

Continue reading

Schematic Design Phase moving along

On Tuesday, May 1, the Building Committee met with representatives from ISG and WEB Construction for an update on the progress that has been made in the “Schematic Design Phase” of our building project. During this phase the architects and designers from ISG have been meeting with user groups to...

Continue reading

Building Committee Update – April 22

Contracts have been signed between Mt. Olive and ISG as architects for the project and with WEB as Construction Manager at Risk (CMAR). A loan agreement has been signed with the bank to cover our current mortgage, the amount approved by the voters for the building project when construction begins,...

Continue reading

We are off and running to reach the goal

Members of Mount Olive – Fundraising has begun for the Building On Our Mission expansion project! For all those who have made ‘pledges of intent’ towards the Building on Our Mission campaign, or wish to support the project, NOW is the time to begin making your gifts! Through March 31,...

Continue reading

Building program moves into Phase II – Design Development

The “Building on our Mission” program has moved into Phase II – Design Development. As noted in our last update, “This phase will involve the engineering, interior design, and architectural teams at ISG working together to research building system and material options to ensure that everything can be integrated easily...

Continue reading

Meeting with architect and target dates for new construction

The Mt. Olive Building Committee met with architect Bryan Paulsen on Thursday, January 25 and can now report the following to the congregation: 1. The loan commitment papers have been signed securing today’s desirable interest rate. 2. Bryan Paulsen (ISG architects) provided a TARGET (not definitive) timeline for the project...

Continue reading