Building Project Update – July 12, 2019

New addition:

  1. Drywall is going up in the new narthex.
  2. The track for the glass wall has arrived and been installed.
  3. Painting in areas beyond the narthex largely completed. Cabinetry beginning to be installed. Plumbing in progress.

Sanctuary and existing narthex:

  1. The sprinkler system has been installed and painting of the pipes is nearing completion.
  2. Storage, data and filming rooms between the sanctuary and the old narthex have been framed in and drywall is hung. Following inspection of electrical, taping of the drywall will begin.

Looking ahead in July:

New addition:

  1. Taping drywall in the narthex mid to late July with painting to follow.
  2. Installation of wood ceiling in narthex following painting of walls.
  3. Finishing all work above the ceiling in the areas beyond the narthex with inspection to follow.
  4. Ceiling tile can be installed in those sections following approval.
  5. Flooring installation will follow ceiling work.
  6. Exterior brickwork, metal panel installation and metal coping trim will be ongoing during July.

Sanctuary and existing narthex:

  1. Worship will continue to take place in the gymnasium.
  2. The east and west walls of the sanctuary will be finished and painted.
  3. Organ will be installed and several pews relocated.
  4. The floor will be thoroughly cleaned and refinished while the pews are out.