Building Project Update – December 17, 2018

The steel deliveries have begun and columns and beams are beginning to be set with bar joists and roof deck to follow. The plan is to have all of the steel up before January 1. With the cooperation of deliveries and weather, framing the exterior walls will begin January 2 with a tentative goal to complete the framing and roof deck by the end of January.
During the school break period from December 19–31 WEB Construction will coordinate subcontractors for electricity, plumbing, and the sprinkler system to bring those utilities from the basement across our current facility to the new construction. This will involve removing ceiling grid and panels in the hallway and possibly the social hall. The grid and panels will be replaced when that project is completed.